The 14.5km-long Tunnel Number 8 forms part of the 125km Rishikesh-Karnaprayag Broad Gauge Rail Link, under construction for Indian state-owned Rail Vikas Nigam.
The breakthrough was achieved by a single-shield Tunnel Boring Machine (TBM) named Shakti, with a 9.11m-diameter bore head, making it the largest TBM to be deployed in the Himalayan region.
Shakti excavated 10.4km of the tunnel. The remainder was completed using the new Austrian tunnelling method.
The railway will connect Rishikesh, Devprayag, Srinagar, Rudraprayag, Gauchar and Karnaprayag across five Himalayan districts, cutting the current travel time from seven hours to two. It aims to improve Uttarakhand’s tourism and economy.
SV Desai, L&T’s director of civil infrastructure, said it was a “significant breakthrough in one of the most challenging terrains”, reflecting strong collaboration with the client.
L&T has previously worked on the second package of the rail line, which included 26.6km of tunnel excavation, building two railway bridges, one road bridge and embankments.
Subscribe here to get stories about construction around the world in your inbox three times a weekFurther Reading:
India’s first high-speed railway on track after land acquisition Tunnel bored on India’s Himalayan super-highwayIndia’s longest railway tunnel breaks through Global Construction Review.
Read More Details
Finally We wish PressBee provided you with enough information of ( India’s longest railway tunnel breaks through )
Also on site :
- ‘Up close and personal’ – Taylor Swift and Travis Kelce share intimate date night as onlooker gives insight into romance
- Italy holds referendum on easing citizenship rules
- Ukrainian drone attacks force Moscow airport closures