Western Sydney International Airport opens after Bechtel-delivered programme finishes seven months early

Western Sydney International Airport (WSI) has opened to passengers seven months early. Western Sydney Airport Corporation led the design, construction, and commissioning programme with Bechtel Australia as delivery partner.

Jetstar operated the airport’s first commercial passenger service, flying from WSI to the Gold Coast.

    Passenger operations follow the start of freight services in July and cap 15 years of planning, seven years of construction and a year of testing and operational readiness.

    “I offer my warm congratulations to our partner, Western Sydney Airport Corporation, our contractors, and all the colleagues and partners who have come together to make this project such a success,” said Darren Mort, president of infrastructure and executive director at Bechtel.

    “WSI shows what the integrated model can achieve when a customer, delivery partner, and contractors work as one team around a clear vision. Together, we transformed a 1,780-hectare greenfield site into a modern international airport, months ahead of schedule.”

    21 million hours worked

    The programme saw more than 21 million hours worked, most of them in high-risk construction, completed with strong safety performance and supported by more than 42,000 proactive safety activities.

    Building the airport involved Australia’s biggest earthworks programme: moving some 28 million cu m of material across the site.

    The project involved Australia’s biggest earthworks programme: moving some 28 million cubic metres of material across the site. Image courtesy of Bechtel

    The team reused nearly six million tonnes of sandstone from Sydney tunnelling projects, diverting material from landfill.

    A 4.5MW solar system was installed that will offset more than 4,000 tonnes of carbon dioxide each year, alongside all-electric heating, rainwater harvesting and electric-vehicle infrastructure.

    Commissioning involved integrating more than 60 software platforms for airport operations, passenger processing, security, retail and office systems.

    Controlling all packages

    Bechtel has been the delivery partner on the project since 2018, helping to set the programme’s scope, cost and schedule baseline. It procured and managed contractors for the earthworks, terminal, runway, landside and technology packages, managing the interfaces between them.

    It also controlled the programme budget, keeping every package moving toward the same completion date, which resulted in completion months early and within budget.

    The airport is designed initially for up to 10 million passengers a year, with capacity to expand as demand grows.

    Western Sydney International Airport opens after Bechtel-delivered programme finishes seven months early Global Construction Review.

    Hence then, the article about western sydney international airport opens after bechtel delivered programme finishes seven months early was published today ( ) and is available on GCR ( Middle East ) The editorial team at PressBee has edited and verified it, and it may have been modified, fully republished, or quoted. You can read and follow the updates of this news or article from its original source.

    Read More Details
    Finally We wish PressBee provided you with enough information of ( Western Sydney International Airport opens after Bechtel-delivered programme finishes seven months early )

    Apple Storegoogle play

    Last updated :

    Also on site :

    Most viewed in News