For more than 100 years, the Sacramento weir has helped protect the region during strong winter storms.
Bernardy helps manage the state's network of weirs.
In 2023, the U.S. Army Corps of Engineers began expanding the weir by an additional 1,500 feet to nearly double the amount of water that can bypass the river.
"You're dealing with underground, you're dealing with earth and nature forces, and so you want to make sure that you get that right," Bernardy said.
"The important part is to make sure that that thing is performing and works the way that it was designed to do, and if that takes adjustments in the field, then that's what it takes," Bernardy said.
"I am confident that the corps team will be able to resolve whatever construction issues they have out there," Bernardy said.
The Army Corps says so far, the complication has not changed the overall price tag of the weir. They hope to complete an analysis of the construction issue by the end of this month.
Hence then, the article about 350 million sacramento weir project faces setback over unstable ground was published today ( ) and is available on CBS sacramento ( Middle East ) The editorial team at PressBee has edited and verified it, and it may have been modified, fully republished, or quoted. You can read and follow the updates of this news or article from its original source.
Read More Details
Finally We wish PressBee provided you with enough information of ( $350 million Sacramento weir project faces setback over unstable ground )
Also on site :