ExxonMobil is delaying the start-up of its joint venture Golden Pass LNG export project in Texas to late 2025 from the first half of next year after work at the facility stalled following the bankruptcy of the lead contractor, Exxon’s CFO Kathy Mikells told Bloomberg in an interview on Friday. The delay in the timeline for the start-up means that Exxon and its partner in the project, Qatar’s state firm QatarEnergy, will launch the export plant about six months later than originally scheduled, Mikells told Bloomberg. In a setback for…
Hence then, the article about exxon delays startup of 10 billion golden pass lng export project was published today ( ) and is available onOILPRICE ( Middle East ) The editorial team at PressBee has edited and verified it, and it may have been modified, fully republished, or quoted. You can read and follow the updates of this news or article from its original source.